Faryon Bridge Rehabilitation
Accordion Title
What work is being done on the Faryon Bridge?
Trent University is undertaking a rehabilitation of the Faryon Bridge to extend the lifespan of this vital piece of campus infrastructure by an estimated 40 years. Planned work includes replacing the deck and balustrades, restoring beams, arches, piers and foundations, as well as other components to ensure the bridge’s integrity while preserving the original architectural design.
Accordion Title
When is the rehabilitation work starting?
Restoration is expected to begin in 2026, following final approvals from the Board of Governors.
Accordion Title
Why is this project necessary?
The Faryon Bridge is a key connector on Symons Campus, supporting academic, research, operational, and utility functions. Ongoing assessments identified the need for structural repairs to maintain safety and ensure the bridge’s continued use for decades to come. The project was approved as part of Trent’s five-year capital plan in 2022.
Accordion Title
Will the design of the bridge change?
No. The rehabilitation work will ensure the bridge maintains its original architectural character and cultural significance.
Accordion Title
How will the project affect mobility on campus?
The bridge will remain open and accessible throughout the rehabilitation. Any temporary closures or interruptions will be communicated in advance.
Accordion Title
When is the work on the Faryon Bridge expected to be finished?
An estimated time frame for completion will be shared once the start date for the rehabilitation work is confirmed.
Bird Netting Installation (Completed Spring 2025)
Accordion Title
Why was netting installed under the bridge this spring?
To prepare for rehabilitation work in 2025, exclusionary netting was installed March 31–April 4 to prevent migratory birds from nesting under the bridge. This minimizes disruption to wildlife once construction begins.
Accordion Title
Who is overseeing the netting work?
Trent is working with Montrose Environmental and RJC Engineers to ensure the netting follows best practices in wildlife protection.
Accordion Title
Will the netting harm the birds?
No. The netting simply deters birds from nesting under the bridge. Migratory birds are expected to nest in alternate nearby locations. The netting was installed in early spring to be in place before any birds nest under the bridge.
Accordion Title
What species typically nest under the bridge? Are they at risk?
While birds do use the underside of the bridge, none of the species known to frequent the area are currently designated as species-at-risk.
Accordion Title
Was campus traffic affected by the netting installation?
Minor, short-term interruptions were expected. On the East Bank, periodic lane closures occured on Nassau Mills Road, with one lane remaining open at all times. On the West Bank, parts of the President’s Walk were temporarily impacted. The bridge was open and accessible during this work, and advance notice was provided about any work taking place on the bridge affecting pedestrian traffic.
Accordion Title
How long did the installation of netting take?
The netting was installed between March 31 and April 4, 2025.